2009: FutureFlow Alliance project completed

In December 2009, GMW’s FutureFlow Alliance project was completed.

The alliance saw GMW partner with various infrastructure businesses to undertake significant irrigation modernisation works in the Goulburn Murray Irrigation District.

The $290 million project involved the installation of 1680 flume gates, 3740 meters and 27km of pipeline, as well as the removal of hundreds of unused assets.

The project was awarded the 2009 Infrastructure Project Innovation Award by the Australian Water Association.

The following year it would win the Award for Project Innovation from the International Water Association.