All Ground Disturbance work shall be planned, monitored, and reviewed by the Supervisor/Field team leader.
Worksafe notification is required in writing prior to excavating greater 1.5m at least 3 working days prior to works commencing
A safe start / risk assessment is required prior to conducting any ground disturbance work
Before ground disturbance work is commenced in any location, the person in control of the workplace (PICOW) shall ensure that:
- Implement an emergency plan compiled in consultation with relevant workers;
- Risk Assessments, SWMS, DBYD, GMW permits or relevant external permits i.e gas, GVW etc have been completed, communicated and signed by all workers onsite
- The hazards of the location have been identified and reported
- Controls for managing all hazards are in place
- The plant being used to excavate is fit for purpose
- The equipment is located so that, in the event of malfunction of the equipment, a collapse or unsafe hazard is not created
- There is no inherent hazard due to the nature of the area on which the excavation work is to be performed
- Relevant stakeholders are informed.
3.5.1 Isolation of Services
If working on or above, or very close proximity, this will be in line with the risk involved i.e. HV is high risk, 12 mm water tapping is low risk. Where high risk and isolation is not practicable then pot holing will be required to accurately locate the service.
Refer to Overhead/Underground Fatal Risk Procedure
Further requirements maybe attained from the asset owner.
3.5.2 Barricades
Suitable barriers and warning signs must be installed if any person is at risk of harm in the ground disturbance area. The nature of barricades will be determined during the risk assessment. The person in control of the works is responsible for ensuring barricades are in place, as outlined in a risk assessment. They are also to ensure that at the end of the work day that the site is to be secure.
3.5.3 Communications
An effective communication system based on two-way acknowledgement between mobile plant operators and ground personnel must be established and communicated before work commences.
3.5.4 Emergency Plan
An Emergency Plan shall be developed when the risk assessment identifies the requirement for an Emergency Plan to be developed. The Emergency Plan is to deal with unexpected incidents, such as ground slip, flooding, gas leaks and the rescue of workers from an excavation. All operators must be trained in this Emergency Plan and regular rehearsals are to be conducted. Review of the Emergency Plan should be conducted daily before work commences and/or if the conditions should change and a walk through of the plan conducted at regular intervals throughout the life of the job/project.
In the event of a collapse, immediately contact Emergency Services (000) and implement emergency response plan. Details are to be included in the jobs Emergency Plan.
3.5.5 Injury Reporting
Any injuries are to be reported to your immediate supervisor onsite first, followed by a notification to OccCorp.
3.5.6 Controlling the Risk
The ways of controlling the risk of Ground Disturbance work are ranked from the highest level of protection and reliability, to the lowest. This ranking is known as the hierarchy of control. The hierarchy is to be used to select the control that most effectively eliminates or minimises the risk for the related circumstances. This may involve a single control measure or a combination of two or more different controls.
3.5.7 Spotter
For any excavation or trenching work being conducted around utilities where either a risk assessment or authority requires a spotter is to be present.
The role of the spotter is to check adjacent equipment and observe practices to ensure that they are being conducted safely and the work activities do not affect any utility asset
NOTE: The Spotter does NOT simply conduct periodic checks; it is a continuous and thorough inspection and presence in the area and its vicinity by the assigned personnel, with special attention being given to any new developments that might affect the safe condition of operations.
3.5.8 Safety Observer
Safety observers may be required on ground disturbance activities to manage and control exclusion zones where members of the public or other workers may be exposed to the risk of being struck by the excavation equipment or ground disturbance. The Safety Observer, will have similar requirements to the Spotter.
3.5.9 Access and Egress into Trench or Excavation
Persons shall not enter or direct another person to enter any trench or excavation unless control measures, identified by a risk assessment have been implemented.
Specifically, hazards associated with the following potential events are to be identified, risk-assessed and control measures implemented as part of the Safe Work method Statement:
- An emergency response plan must be developed prior to undertaking the activity
- A person shall not step nor jump over an excavation or trench
- A person being trapped by the collapse of the excavation or trench
- A person being struck by an object falling into the excavation or trench
- A person falling into the excavation or trench
- A person must not walk within 0.5m from the edge of an excavation or trench unless actually conducting a specific task
- A person inhaling, or otherwise being exposed to, airborne contaminants, fumes and gases in the excavation or trench.
A safe means of access in and out of a trench or excavation must be available at all times, as outlined in the SWMS.
Ladders are to be used to enter and exit trenches as per the requirements outlined in the Risk of Falls Procedure (A4003981). Ladders must be no more than 9m apart and at least 1m of the ladder must extend out of the trench and secured
While carrying out any excavation work, the following requirements apply:
- Each person associated with the work shall follow the precautions to be taken as specified in the relevant risk assessment and SWMS as per the site safety requirements
- No person shall enter an excavation or trench where the head & shoulders are below the edge / top of the excavation to carry out work alone if the excavation is not benched, battered or shored or if there is a risk of engulfment
- A documented site inspection must be carried out each day prior to work commencing or if site conditions change before work can commence.
- Equipment or plant that produces fumes or gases that may result in creating a hazardous atmosphere within the excavation is not to be used. Where alternative equipment cannot be identified, mechanical ventilation increasing air circulation is to be installed prior to a worker entering the excavation / trench
3.5.10 PPE
PPE must be appropriate to the task performed as outlined in the Personal Protective Equipment Procedure. As a minimum this will include ankle high laced safety boots (or safety gumboots), long-sleeve high visibility clothing (orange, sleeves rolled down), drill long pants, gloves to be carried onsite at all times, hard hat with a wide brim, clear/tinted safety glasses, sunscreen, hearing protection, and any others as identified in a risk assessment.
3.5.11 Plant and Equipment
Petrol or diesel equipment such as vehicles, generators and pumps must not be used in or near the trench if there is a risk of exhaust fumes entering an excavation that is or will be occupied by personnel (refer to Confined Space Procedure), or a risk of flammable mixtures igniting.
Areas in which plant and equipment is required to be operated should be adequately assessed for all potential risks for example, ground composition and materials, geographical location, ground compaction & stability, location of existing services, vibration caused by the plant, human interaction etc.
3.5.12 Excavation Stability
Controls for maintaining the stability of disturbed soil during excavation activities shall be in place. Engineering controls such as battering, benching, shoring or shielding shall be used to support or stabilise the faces of the excavation to prevent collapse and harm, as determined by the risk assessment or at trench depths greater than 1m
If the trench depth is planned at 1.5m or greater, Worksafe (Vic) must be notified 3 days prior to the commencement of works. Where the depth is not planned and the excavation reaches 1.5m or greater the works must cease and Workcover must be notified and confirmation received prior to recommencing work
Shoring & Shielding controls shall be designed and prepared by an appropriately qualified person (current trenching and shoring training) and comply with the WorkSafe Compliance Code - Excavation 2019.
Any support systems shall be removed in a way that protects workers from cave-ins, structural collapse or being struck. Temporary structural measures may be required during the removal process.
For trenches deeper than 3m, written approval by a geotechnical engineer must be obtained stating that the trench is safe to work in. The approval must be kept on site at all times during the work activity.
3.5.13 Excavation Activities
Mobile plant, materials and spoil must be kept at a distance of 1m or more from the excavation edge to prevent potential hazards to the person working in the excavation (refer to the Mobile Plant Procedure). Vibration from external sources such as roads and railways may need to be considered in the risk assessment.
3.5.14 Dewatering
Dewatering operations must be performed where there is a risk of excess water accumulating around the excavation. Dewatering tasks shall be included in the SWMS/Risk Assessment.
3.5.15 Placement of Spoil
Excavated spoil must be placed at least 1m away from the edge of the excavation, and that shall be no higher than 1m.The further away from the excavation the higher the pile can be stacked. Noting that higher spoil piles will require further environmental considerations such as but not limited to dust suppression, sediment run off etc. The Project Manager shall determine through a risk assessment whether a geological load bearing test is required.
3.5.16 Backfilling
Backfilling and rehabilitation requirements shall be determined by the Supervisor/Field Team Leader prior to excavation works commencing.