The following completed documents must be submitted to the Asset Owner for approval prior to working on any live asset (when in the line of fire):
- Permit and Risk Assessment
- Isolation Plan or a Standard Isolation process
3.1.1 Risk Assessment
Lock out and/or tag out of assets for routine inspections, repairs, maintenance, assessments, adjustments or cleaning should not be undertaken until a risk assessment is completed by the team comprising both the work party as well as the asset owner, operators and relevant subject matter experts.
The risk assessment will be conducted using the risk assessment template as part of an Isolation Plan or a Standard Isolation Process.
A documented risk assessment must be completed to determine:
- What stored energy sources are present
- What risks are associated with known hazards or stored energy sources
- What controls are implemented to remove all harmful sources of stored energy to make it safe
- To Identify the isolation points required for the task/job to be undertaken safety
When the risk assessment identifies stored energy sources, the Hierarchy of Control must be used in conjunction with GMW Hierarchy of Isolation to ensure the task/job can be undertaken safely.
3.1.1.1 Hierarchy of Control
The hierarchy of control is a system for determining, designing and applying risk controls to activities in the workplace:
- Elimination - Highest level of protection and most effective control
- Eliminating the hazard and the risk it creates is the most effective control measure
- Substitution
- Substitute the risks with lesser risks
- Isolation
- Isolate people from the risks
- Engineering
- Reduce the risks through engineering changes or changes to systems of work
- Administration
- Administrative controls / actions to minimise exposure to hazards and to reduce the level of harm
- Personal Protective equipment (PPE)
- Personal protective equipment (PPE) to protect people from harm
3.1.1.2 GMW Hierarchy of Isolation
GMW’s preferred isolation method is Double Isolation and test for dead. Where this cannot be achieved, the below GMW Hierarchy of Isolation must be adopted.
- Double Isolation
- 2 x Isolations applied and system tested for dead
- Permit application will include an Isolation Plan or a Standard Isolation process
- 1 x Isolation and 1x Control
- 1 x Isolation applied and system tested for dead
- Permit application will include an Isolation Plan or a Standard Isolation process
- 1 x Isolation
- 1 x Isolation applied and system tested for dead
- 2 x Controls
- Permit application will include an Isolation Plan or a Standard Isolation process
- 1 x Control = Live work
- Permit application will include an Isolation plan or a Standard Isolation process
- Risk assessment, requires written approval from the General Manager of the Division responsible for conducting the works via the LOTO Approval Form A4892865 and will require an emergency / rescue plan.
All isolations and controls must be deemed appropriate and effective and tested for dead prior to work commencing.
3.1.1.3 Isolation versus Control
An isolation involves the physical interruption of the stored energy source and applying a Lock and Tag.
A control involves a process for monitoring the stored energy source to ensure that it does not pose a risk.
Where a control is to be applied, there must be an allowance for adequate time between the control being triggered and the activity that is required from the working group (i.e. vacating the worksite).
Where only one control can be achieved, the work is to be considered “ Live work”.
Note: No live work will be conducted without the approval of the General Manager of the Division conducting the works until all documentation has been submitted for assessment / evaluation to ensure all other options have been exhausted. (Live Works form must be completed)
3.1.1.3.1 Live Work
Prior to any live work being conducted the permits should be accompanied by:
- A risk assessment of the live work activity in consultation with any HSRs or contractors who will be undertaking the “Live Work”
- Confirmation that training, information and supervision has / will be provided to all workers either conducting or that are exposed to the live work prior to the live works being conducted
- Safe work instructions / SWMS relevant to the activities relating to live work have been reviewed
- Written approval from the General Manager of the Division responsible for conducting the works via the LOTO Approval Form A4892865
- Where the risk level associated with the “live work” is determined to be medium or high, a copy of an emergency / rescue plan must also be approved by the responsible General Manager.
Any testing or monitoring of equipment in an energised state required for maintenance purposes including but not limited to commissioning must only be conducted by a suitably qualified person and have as a minimum a safe work instruction and risk assessment for the activity. An Electrical Safety Procedure is scheduled to be developed to further clarify the testing and monitoring expectations.
3.1.2 Isolation Plan
An isolation plan is a set of steps to be followed to keep assets from being set in motion or to prevent the release of any form of stored energy while work is being completed. Isolation plans are to be developed by the workgroup with responsibility for the asset (in most instances, this will be the asset owner).
When developing Isolation Plans, consultation with relevant subject matter experts must be undertaken to ensure that the process is robust and considers all possible scenarios for the inadvertent release of stored energy.
The effectiveness of an isolation plan relies on:
- Having the isolation plan documented and accessible to the relevant people in the workplace
- Ensuring that the appropriate SME’s from all relevant parties are involved in the development of the isolation
- Ensuring that Third Party Organisations (where applicable) are involved in the development of the isolation (in regard to their asset only)
- Providing information, instruction and training to workers involved with the isolation and/or scope of work
- Appointing a person as a Site Works Supervisor (Permit Owner) to make sure the workplace strictly follows isolation plan
- Walking the isolation to ensure that all sources of energy have been identified, controlled and that the isolation will be effective
GMW documented isolation plans must contain:
- All isolation steps required to safely remove the asset, from service
- Any points where work should pause and be assessed by all relevant parties. E.g. Specific stages of a projects
Isolation Plans must:
- Be peer reviewed before being carried out
- Be communicated with all relevant parties involved including contractors
- Available at the worksite for the duration of the activity
- Have the correct approvals
3.1.3 Standard Isolation Process (SIP)
A Standard Isolation Process is a plan that has been developed to perform an isolation that is routinely completed. It is a set of steps to be followed to prevent assets from being operated or to prevent the release of any form stored energy while work is being completed. Standard Isolation Processes are to be developed by the workgroup with responsibility for the asset (in most instances, this will be the asset owner).
When developing Standard Isolation Processes, consultation with relevant subject matter experts (SME’s) must be undertaken to ensure that the process is robust and considers all possible scenarios for the inadvertent release of energy.
The effectiveness of Standard Isolation Process relies on:
- Having the SIP documented and accessible to the relevant people in the workplace
- Ensuring that the appropriate SME’s for all relevant parties are involved in the development of the isolation
- Ensuring that Third Party Organisations (where applicable) are involved in the development of the isolation (in regards to their asset only)
- Providing information, instruction and training to workers involved with the asset,
- Appointing a person as a supervisor (Permit Owner) to make sure the activity strictly follows SIP
- Conducting a review to ensure that the SIP is relevant to the scope of work
- Walking the isolation to ensure that it will be effective
GMW documented Standard Isolation Processes must contain:
- All isolation steps required to safely remove the asset from service
- Any points where work should pause and be assessed by all relevant parties
SIP’s must be:
- Peer reviewed before being carried out
- Communicated with all relevant parties including contractors
- Reviewed every two years at a minimum or where there has been a change to the design of the asset that is being isolated, there is a change to the scope of work or there has been a change to the process
- Signed off by the appropriate GM once all SME’s have agreed on the process.
3.1.4 Permit
The permit process ensures that GMW’s isolations meet the ‘Principles of Isolation’. The permit can represent a standalone isolation or it can represent a master isolation with secondary isolations that are associated. The permit identifies the isolation process which is as follows:
- The scope of work and the assets involved
- The stakeholders
- Identification of all energy sources
- Identification of all isolation points; and/or
- Documented controls
Where energy sources are identified, all works must have a corresponding permit and include an Isolation Plan or a Standard Isolation Process. The permit covers:
- Isolate all energy sources
- De-energise all stored energies (Test for dead)
- Lock and Tag all isolation points
- One person per lock/one key per lock,
- Multiple Isolations (More than one energy source)
- Tagging
- Testing of Isolation Procedures
- Re-energising and re-instating
Where control(s) are used within the Isolation Plan, they must also be:
- Inspected for implementation
- Regularly inspected for effectiveness during works
- Removed / checked before re-energizing and re-instating
Where only one control can be achieved, the work is to be considered “Live work”.
An isolation permit must include an expiration date. If the works are not completed within the original allocated timeframe, a new permit will be required. A new permit will also be required where there is a change of the scope of works from what was originally proposed.
3.1.4.1 Locking Single & Multiple Isolation Points for One Isolation Permit
Asset Owner
- Apply Isolation Point Lock(s) and ‘Out of service’ tag(s) to each Isolation Point
- Retain any key(s) to the noted Isolation(s)
- Inspect all the isolation points with locks and verify isolations are effective
Site Works Supervisor
- Apply Isolation Point Lock(s) and ‘Danger – Do Not Operate’ tag(s) to each Isolation Point
- Select required isolation equipment required to satisfy the Isolation Plan; this may include:
- Lock Box
- Hasps
- A number of personal locks
- Place the Isolation Point Lock key(s) (Permit Owner’s) in the Lock Box and closes box
- Attach a SWS lock to the Lock Box and retains the key
- Inspect all the isolation points with locks and verify isolations are effective
- Shows the Work Party Members all of the isolation points with locks
- Lock on and lock off daily or when moving to another job
Work Party Members
- Sign on to the Isolation Permit and attaches their Personal Safety Lock and tag to the group isolation point
- Lock on and lock off daily or when moving to another job
3.1.4.2 Locking Isolation Points Shared Across Isolation Permits
Asset Owner
- Apply Isolation Point Lock(s) and ‘Out of Service’ tag(s) to each Isolation Point
- Retains any key(s) to the noted Isolation(s)
- Inspect all the isolation points with locks and verify isolations are effective
Site Works Supervisor
- Identify the Master Isolation Permit and associated Lock Box which contains the isolation points required for any secondary Isolation Permits
- Apply Isolation Point Lock(s) and ‘Danger – Do Not Operate’ tag(s) to each Isolation Point
- Select required isolation equipment required to satisfy the Isolation Plan; this may include:
-
- A number of personal locks
- Locks Cascade Lock onto the primary Isolation Permit Lock Box and places the key into the Lock Box for any secondary Isolation Permits along with Isolation Point Locks key(s) (SWS) in the Lock Box and closes box
- Attach a SWS lock to the Lock Box and retains the key
- Inspect all the isolation points with locks and verify isolations are effective
- Shows the Work Party Members all of the isolation points with locks
- Lock on and lock off daily or when moving to another job
Work Party Members
- Sign on to the Isolation Permit and attaches their Personal Safety Lock and tag to the group isolation point
- Lock on and lock off daily or when moving to another job
3.1.5 Workshop Maintenance
Where vehicles, plant and equipment are subject to repairs, maintenance or servicing, the workshop technicians will remove the keys from the equipment and they will be secured to prevent unauthorised access. Prior to work being undertaken, all sources of stored energy will be identified and appropriately controlled or dissipated.
Once work is completed, the keys can be returned to the equipment provided the responsible technician has verified that all systems/components of the equipment are safe to operate.
*Note: Personal Isolation Locks must never be keyed alike
Lock type |
Description |
Image of Locks |
Image of tags |
3.2.1 Black Locks - (Asset Owner)
|
Asset Owner Locks are BLACK and:
- Will only be issued to asset owners who have completed GMW level 2 training on energy Isolation,
- They are the first and last lock to be added to or removed to an asset isolation
- An “out of service” tag is also to be fitted with the asset owners isolation lock
- The asset owner’s lock can be an individual lock or a team lock; this is to be specified on the Isolation Permit (Asset Owner Sign Off Section)
- Where an asset lock is individual, a handover process must be conducted and tags/information changed if the individual changes
- Must be implemented if work is being performed by the same Division
- Where a lock is a team lock, the tag should be marked as such
- May be implemented if work is being performed by a different Division or Contractor
- Any member of a Black Lock Team interacting with an isolation must be familiar with that specific isolation
** The person who places the asset owners lock cannot also assume the role of the Supervisor
|
 |
 |
3.2.2 Site Works Supervisor / Permit Owner (SWS/PO) Lock
|
Site Works Supervisors/Permit Owner (SWS/PO)
- Lock is blue
- Will only be issued to workers who have completed GMW level 2 training on energy Isolation,
- Can be used by the SWS/Permit Owner in replacement of their personal Red Lock
- Can remain in place over the course of the permit or as an overnight lock
- One person, one lock
- One lock, one key
- Must be installed/removed by SWS/Permit Owner
- Is to be fitted with “Danger, do not operate tag
Changing of Locks/Tags
- When work is occurring, there must always be an SWS lock and Tag on the asset. Where work is being conducted over multiple shifts, the SWS /Permit Owner must conduct a physical handover with the incoming SWS/Permit Owner at the location of the SWS/PO Lock
- The incoming SWS lock must be placed before the outgoing lock is removed.
|
 |
Tag used while Workers are in the line of Fire
 |
3.2.3 Red Locks - Personal Safety Lock (PSL
|
Personal Safety Locks (PSLs) Personal Safety Locks are RED and:
- Will only be issued to workers who have completed GMW training on energy Isolation,
- Are individually keyed
Every individual working on the asset must place their own personal red lock and a “Danger, do not operate” tag. Locks and tags
|
 |
Tag used while Workers are in the line of Fire
 |
3.2.4 Yellow Locks - Maintenance Lock
|
Maintenance Locks are YELLOW and:
- Will only be issued to workers who have completed GMW training on energy Isolation,
- Will be locked onto isolation points to keep assets in an isolated state when it is under maintenance.
- An “out of service” tag is also to be fitted with the asset maintenance lock.
- Is to be fitted to an asset along with the red personal locks of each person working on the asset.
Can be used to secure an asset overnight but personal locks must be removed to indicate that there is no individual in the line of fire.
|
 |
 |
Collection of Locks & Tags
The store (Cussen St) will hold energy isolation equipment for business units, groups, or individuals to collect. Training will be required prior to being issued with locks & tags.
Requirements when collecting LOTO equipment from the store
Where a worker has been requested to collect multiple items of LOTO equipment for employees on behalf of a manager/supervisor, the Equipment Release Form (A4872943) must be signed as authorisation that the manager/supervisor will be taking responsibility for distributing the locks and tags etc. to the workers who have completed required/relevant ELMO LOTO modules.
Specialised LOTO equipment
Under certain circumstances, specialised equipment may be required to effectively perform an isolation. The type of equipment required may be determined based on specific risks such as high voltage/electrical, the presence of non-lockable valves, the absence of appropriate locking mechanisms on cabinets etc.