The Victorian Floods and their impact

In Victoria in late 2010 and early 2011 most water catchment systems experienced the highest inflows recorded since 1993, as a result of a series of high rainfall events. The resulting floods were widespread over central and northern Victoria, and had a significant impact on urban communities, agricultural areas and the natural environment.

Between September 2010 and February 2011 G-MW experienced flooding across most of its operating regions with record flooding in both the Loddon and Campaspe catchments. The floods covered some 16,000 square km of G-MW's service region, with approximately 3,000 km of its channel network affected. Infrastructure was damaged and recreational areas were affected by floodwaters.

G-MW customers, staff and communities in our service area were all impacted in some way by the damage caused by these events.

Why Did the Storages Spill?

G-MW manages 16 large dams across Northern Victoria. By late 2010 most of the dams managed by G-MW were full as a result of winter and spring rains. As further heavy rainfall events occurred, stormwater runoff caused flooding in the upper catchments which flowed into the dams. These floods were passed through the dam spillways.

What is the Purpose of the Storages G-MW Manages?

G-MW's storages are designed and operated to harvest, store and release bulk water for downstream entitlement holders. The dams are neither intended nor designed to be used for flood mitigation purposes, although G-MW operates the dams to reduce flood impacts where possible.

Managing Floods Through Dams

G-MW dams are operated in accordance with flood operations procedures which comply with the requirements of the bulk entitlement orders. The bulk entitlement orders provide conditions under which G-MW can release water from dams; there is no scope given to release water from a dam for flood mitigation purposes except for Lake Eildon.

However, where G-MW can be reasonably assured that a pre-release can be made without adversely impacting on water resource availability then pre-releases are made from dams with gated spillways (Eildon, Cairn Curran and Buffalo).

Pre-releasing water from full or near-full storages will only be effective for relatively minor flood events, and must be managed so as to not aggravate flooding further downstream. During each of the 2010/11 flood events, water was pre-released from Cairn Curran.

Throughout the flood events G-MW maintained regular contact with VICSES, local government and the Bureau of Meteorology to provide operational advice to the flood response efforts.

How did the Flood Impact on G-MW Assets?

Once the scale of the predicted weather event and its likely impact on G-MW's systems was evident, G-MW staff worked long hours in co-ordination with other agencies under very trying circumstances to ensure that impact of the flood water was reduced for the whole region, and to minimise damage to G-MW assets.

The floods impacted on three key storages controlled by G-MW - Laanecoorie and Cairn Curran Reservoirs (both Loddon system), and Lake Eppalock (Campaspe system). Tullaroop Reservoir was impacted to a lesser extent.

During major floods, G-MW shuts down the irrigation channel network by closing regulating structures. This allows overland floods to follow natural flow paths and aims to prevent flood water being transferred along channels and affecting other landowners.

G-MW's channel systems were significantly affected by the flooding, with many of the earthen channel banks washed away. Some road bridges owned by G-MW were destroyed and the G-MW customer centre in Rochester was also flooded.

Providing Assistance

It is the role of the VICSES to provide flood emergency management co-ordination as a lead agency. The Bureau of Meteorology's (BoM) role is to monitor river levels and issue warnings as appropriate to G-MW, SES, local shire councils and through media networks to the public.

During flood events G-MW's role is to communicate with these agencies to provide regular information on releases from G-MW's storages. This arrangement is in accordance with the current Victorian Emergency Management Manual.

Working with Other Agencies

In the lead up to increased flows in January 2011 G-MW contributed to an overall flood mitigation strategy for the Kerang Lakes region as well as releasing water from key storages in the area, including:

  • Diverted water via irrigation channels near Kerang into Lake Tutchewop, with the approval of the Murray-Darling Basin Authority (MDBA)
  • Under the direction of the Municipal Emergency Response Coordinator (MERC), G-MW's Number 9 channel was banked off during the flood threat on Swan Hill to prevent water from flowing into town, the Number 10 channel bank in the Tyntynder flats area strengthened and the 14/2 channel bank incorporated with the Town Levee to assist in the protection of the Kerang township.
  • Under the direction of the Regional Incident Control Centre (ICC) in Bendigo, G-MW resources completed urgent inspections on the Kerang town levee and participated in various planning activities.
  • Worked closely with the ICC to ensure that all possible avenues were explored to relieve some of the pressure on storages and channels from the rising floodwater to minimise impacts on the community.

Helping Customers

G-MW immediately started a program of assistance for flood-affected customers. G-MW extended account payment deadlines and provided replacement statements. Information about assistance from Government and other agencies was given and G-MW created a dedicated web page with up-to-date flood status and recovery information. G-MW also provided input to government planning on flood recovery assistance programs. In addition G-MW's Water Wheels Information Van toured the region and G-MW gave regular updates to DSE and the Government to help develop flood recovery assistance.

Recovery

G-MW has repaired or replaced damaged infrastructure and public recreation areas. Dam gates have been repaired or replaced at Laanecoorie, channel banks reinstated and recreation areas cleaned up and repaired. The G-MW office in Rochester has been refurbished with most of the flood damage to the interior of the building repaired.

At 30 June recovery work on channels was 95% complete, with some small areas of channel rectification to occur before the next irrigation season commences.

Following the floods, one of the main issues for the business was the 40 degree heat after the January rain. While some areas were flooding, others required water for irrigation again within days. Repairing channels in order to use them for water supply was a logistical challenge for G-MW. Many staff resources were diverted to assist the recovery effort, including diverting staff from other centres, construction crews and asset assessors to walk channel banks and identify where repairs were needed. External contractors were also engaged to allow repairs to be carried out quickly and efficently.

After the floods, G-MW staff also assisted local councils to identify areas where flood water had ponded, and provided resources to help move it on, particularly in the Benjeroop area.

Moving Forward

Following the January 2011 floods, G-MW attracted considerable criticism from the media and community for perceived inappropriate action in relation to flood mitigation at, in particular, the Cairn Curran and Laanecoorie dams, and Lake Eppalock. This has highlighted the need for further community education on the design, and role of the storages G-MW manages in relation to flood events and the need to reinforce the role of each agency in relation to flood warnings and information updates.

A preliminary internal review has been undertaken, and G-MW is confident that appropriate procedures were followed throughout the incident, and that those procedures remain valid for future safe operation of our assets. G-MW also identified that:

  • Forecast information from the BoM was consistent with similar information provided in previous flood events.
  • Flood level scenario modelling provided by BoM was helpful to gauge the possible severity of the event.
  • Some improvements could be made to streamline internal and external communications.
  • Current level of personnel resourcing for dams operations is adequate to manage significant flood events. 24 hour operating flood rosters were implemented during each event. Rostering staff rest breaks was challenging, but generally was managed.
  • Staff isolation at various sites was anticipated and well managed.
  • Significant public interest at storages created some challenges with public and traffic management.
  • Co-ordination with the ICC was adequate, and mainly maintained through regular situation reports and periodic telephone calls. In future events, G-MW will offer to have a liaison officer embedded at the ICC.
  • Engaging with the public to increase awareness of the possibility of flooding was difficult prior to the November 2010 event, especially amongst new members of the community. Following the event there was significant interest from downstream communities.
  • G-MW experienced significant demand for information updates on flood issues that were unrelated to the operation of our infrastructure, as well as increased requests from landowners to operate irrigation infrastructure to divert floodwaters.

Flood events on the scale of November 2010 and January 2011 are rare (likely to be only one in 100 years). G-MW's operating procedures had never been tested under these conditions. G-MW is engaging an independent review of the dams operating procedures and the use of those procedures during these two flood events. The review is scheduled for completion in September 2011.

Inflows